Every autumn we get the same call. The roof needs doing, the homeowner knows it, and they ask whether they should just wait until spring. Almost always they have been told by somebody that you cannot roof in the cold.
That is not quite right. You can replace a roof through a New Jersey winter, and plenty of roofs go on in January. What changes is not whether it can be done but how it has to be done, and a crew that works through winter the same way it works in July will leave you with a roof that fails early.
Cold causes two separate problems, not one
They get lumped together and they are different. One is about handling the shingle. The other is about whether the shingle ever sticks down.
Problem one: shingles turn brittle
The Asphalt Roofing Manufacturers Association is direct about this. Bundles become brittle in cold conditions and shingles may crack or break, so they recommend storing shingles indoors before application so they go on warm. They also call for extra care, including warming the shingles, anywhere the material has to bend, which means hips, ridges and valleys.
That last point has a practical consequence you can actually check. ARMA recommends using open metal valleys in cold weather specifically to avoid the bending a woven valley requires. If somebody is weaving valleys out of stiff cold shingles in February, that is a corner being cut.
Problem two: the sealant strip needs heat
This is the one that matters most and the one homeowners never hear about. Every architectural shingle has a strip of thermally activated adhesive on it. It is not sticky out of the bundle. It bonds when sun and warmth soften it and the weight of the course above presses it down. That is what makes a roof a sealed surface rather than a pile of overlapping tabs.
In January, that heat does not arrive. The shingles go on correctly, they look right, and the sealant may not bond for weeks or even until spring. Until it does, the roof is far more vulnerable to wind lifting the tabs, which is not a theoretical risk in a New Jersey winter.
ARMA's answer is hand sealing: the shingles can be hand sealed with an approved asphalt roofing cement or another adhesive the manufacturer accepts. It is slower, it costs labour, and it is the difference between a winter roof that holds and one that does not.
What a proper winter installation looks like
- Shingles stored somewhere warm and brought out as they are used, not stacked on the roof overnight
- Tabs hand sealed with a manufacturer approved roofing cement
- Open metal valleys rather than woven, to avoid bending cold material
- No work on a frosted, icy or wet deck, for the crew's safety as much as the roof's
- Self adhering ice and water barrier at the eaves, which matters more in winter than any other time
- Nail guns checked and adjusted, because cold material and cold tools both change how a fastener sets
That last one is quietly important. A nail driven too deep cuts through a cold shingle instead of holding it, and an underdriven nail leaves the head proud so the course above never lies flat. In cold weather the margin between the two narrows.
The days we tell people to wait
There are conditions where we will not start, and we would rather lose the week than argue about it later.
- Active rain, sleet or snow, or a deck with frost on it
- A hard cold snap, where the material will not stay workable long enough to handle safely
- A complex roof with a lot of cut and bend work, where cold material is fighting the crew all day
- A forecast that will not give us a clear enough window to get the deck dried in
A tear off is a commitment. Once the old roof is off, the house is open until the new one is dried in, and that is not a thing to start on the edge of a storm.
Why winter can actually be the better time
Two honest reasons, and neither is a sales pitch.
The first is scheduling. Summer and early autumn are when every roofer in New Jersey is booked. In winter you are not waiting six weeks for a slot, and you get a crew that is not trying to finish you to start somebody else.
The second is that a failing roof does not improve over a New Jersey winter. Freeze and thaw is the most destructive cycle a roof goes through here. Water gets into a gap, freezes, expands, opens the gap wider, thaws, and does it again the next night. A roof with a known problem in November is a worse roof in March, and sometimes the decking underneath goes from repairable to replaceable in a single season.
The one thing that genuinely cannot wait
An active leak. Water coming into the house is not a spring project. Even if the full replacement sensibly waits for better weather, the leak gets stopped now, properly, so the water stops finding insulation, framing and drywall. Everything that water touches costs more than the roof does.
If you are not sure whether your roof will make it to spring, we will come and look and tell you straight. Call 908-880-2500. If it can wait, we will say so, and we will tell you what to watch for.
Sources
- Asphalt Roofing Manufacturers Association, Recommendations for Installation of Asphalt Roofing Shingles in Cold Weather
- GAF Technical Bulletin R-133, Temperature Extremes and Fiberglass Asphalt Shingles
- Building America Solution Center, Pacific Northwest National Laboratory, Attic Air Sealing, Insulating and Ventilating for Ice Dam Prevention
More from the Journal
- Fiber Cement or Vinyl? Choosing Siding for a New Jersey Home
- Ice Dams: Why They Happen, and Why the Fix Is Not on the Roof
- Storm Damage and Your Roof: What to Do First in New Jersey
- What Separates a Good Exterior Job From a Cheap One
- Gutters That Actually Work in North Jersey
- When to Replace Your Roof, and When to Repair It
- How to Check a New Jersey Contractor Before You Sign
- What a Roof Replacement Actually Costs in New Jersey
Ready to Upgrade Your Home's Exterior?
Call 908-880-2500 for a free, no-pressure estimate on your next roofing, siding, or exterior project. Based in Hillside, serving homeowners throughout New Jersey.
Get A Free Quote